Action scheduled
Pedestrian crossing where Tytherington school cross a busy road
Reported via mobile in the Carriageway category by John Cadman Stewart at 06:33, Mon 27 November 2023
Sent to Cheshire East Council less than a minute later. Council ref: 5255125.
Severe flooding. This is a well-known issue for CEC. It has been an issue for years and still CEC has been unable to fix it. It is a danger to the public, especially school children and disabled users of the crossing. This must be fixed as a priority before someone is injured.
Updates
-
Thank you for contacting Cheshire East Highways. We have logged your enquiry and passed it to a member of our team.
Our teams are working hard to manage and respond to reports from members of the public.
We are experiencing a high volume of enquiries and we will be prioritising those issues that present most risk to the travelling public. While we normally aim to provide you with a response within 20 working days, response times for all other reported issues may take longer than usual.
Thank you for your patience.
Posted by Cheshire East Council at 06:33, Mon 27 November 2023
-
We have arranged for jetting work to be carried out. We post our upcoming jetting schedule online and usually update it on a weekly basis. The list shows the schedule for up to 2 weeks in advance. The list might change due to issues such as weather events, so you should check it for any updates. You can find the latest updates online through the following link: https://www.cheshireeast.gov.uk/ highways_and_roads/ road-maintenance/ gullies-and-drains.aspx
State changed to: Action scheduled
Posted by Cheshire East Council at 12:29, Mon 27 November 2023
This report is now closed to updates from the public. You can make a new report in the same location.