In progress
No 28
Reported via iOS in the Pothole category anonymously at 17:49, Tuesday 3 October 2023
Sent to Cheshire East Council less than a minute later. Council ref: 5058204.
The poor repair that your contractors have done twice has failed again
It’s a failure of the structural formation of the road or drainage failure. Needs to be properly investigated instead of just chucking tarmac into the hole
Updates
-
Thank you for contacting Cheshire East Highways. We have logged your enquiry and passed it to a member of our team.
Our teams are working hard to manage and respond to reports from members of the public.
We are experiencing a high volume of enquiries and we will be prioritising those issues that present most risk to the travelling public. While we normally aim to provide you with a response within 20 working days, response times for all other reported issues may take longer than usual.
Thank you for your patience.
Posted by Cheshire East Council at 17:49, Tuesday 3 October 2023
-
State changed to: In progress
Updated by Cheshire East Council at 07:34, Wednesday 4 October 2023
-
Your report has been assessed and we need to carry out some work. You will receive an update once this has been scheduled.
State changed to: Action scheduled
Posted by Cheshire East Council at 13:19, Tuesday 24 October 2023
-
State changed to: In progress
Updated by Cheshire East Council at 12:30, Wednesday 25 October 2023
-
We have assessed the issue and have been unable to identify the cause during our visit. We need to carry our further investigations to fix the problem. We are unable to provide you with a timescale for this work, but will update your report once we have more information.
Posted by Cheshire East Council at 14:07, Wednesday 25 October 2023
This report is now closed to updates. You can make a new report in the same location.