report here Reposition
report here
In progress
Between Edleston road and Brooklyn street
Reported via desktop in the Pothole category by John Rhodes at 17:09, Thursday 26 January 2023
Sent to Cheshire East Council less than a minute later. Council ref: 4174188.
The potholes have been here for months and months. There are at least 10 potholes in this short stretch of vary depths- some have been filled in before and have started to disintegrate, almost immediately. See photos
Updates
-
Thank you for contacting Cheshire East Highways. We have logged your enquiry and passed it to a member of our team.
Our teams are working hard to manage and respond to reports from members of the public.
We are experiencing a high volume of enquiries and we will be prioritising those issues that present most risk to the travelling public. While we normally aim to provide you with a response within 20 working days, response times for all other reported issues may take longer than usual.
Thank you for your patience.
Posted by Cheshire East Council at 17:09, Thursday 26 January 2023
-
State changed to: In progress
Updated by Cheshire East Council at 07:52, Friday 27 January 2023
-
We have assessed your report and have arranged to carry out work as soon as possible.
State changed to: Action scheduled
Posted by Cheshire East Council at 14:20, Tuesday 7 February 2023
This report is now closed to updates. You can make a new report in the same location.