Reported via desktop in the Flooding category anonymously at 15:28, Friday 6 January 2023

Sent to Cheshire East Council less than a minute later. Council ref: 4095581.

Every time it rains the road and pavements flood on both sides and it takes a long time to drain. This is dangerous as cars travel at speed down Leek Road, it is a danger on the road and to passing pedestrians. The road and pavements are flooded on both sides. This is a well used route with children walking to school daily, including people pushing prams getting completely soaked wading through water and being drenched by cars splashing them which is unavoidable. This has been occurring for a very long time and is getting progressively worse, now going into people's driveways.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for contacting Cheshire East Highways. We have logged your enquiry and passed it to a member of our team.

    Our teams are working hard to manage and respond to reports from members of the public.

    We are currently experiencing an increase in demand of reported issues along with a temporary reduction in available staff due to Covid-related sickness and self-isolation.

    During this time and until the situation improves, we will be prioritising those issues that present most risk to the travelling public. While we normally aim to provide you with a response within 20 working days, response times for all other reported issues may take longer than usual.

    Thank you for your patience.

    Posted by Cheshire East Council at 15:28, Friday 6 January 2023

  • State changed to: In progress

    Updated by Cheshire East Council at 11:17, Monday 16 January 2023

  • We have arranged for jetting work to be carried out. We post our upcoming jetting schedule online and usually update it on a weekly basis. The list shows the schedule for up to 2 weeks in advance. The list might change due to issues such as weather events, so you should check it for any updates. You can find the latest updates online through the following link: https://www.cheshireeast.gov.uk/ highways_and_roads/ road-maintenance/ gullies-and-drains.aspx

    State changed to: Action scheduled

    Posted by Cheshire East Council at 13:24, Monday 16 January 2023

  • Thank you for contacting Cheshire East Highways. We have logged your enquiry and passed it to a member of our team.

    Our teams are working hard to manage and respond to reports from members of the public.

    We are experiencing a high volume of enquiries and we will be prioritising those issues that present most risk to the travelling public. While we normally aim to provide you with a response within 20 working days, response times for all other reported issues may take longer than usual.

    Thank you for your patience.

    State changed to: Open

    Posted by Cheshire East Council at 10:23, Monday 24 April 2023

  • State changed to: In progress

    Updated by Cheshire East Council at 10:28, Monday 24 April 2023

This report is now closed to updates. You can make a new report in the same location.