On north side of road at end of hedge line, 1m from road and below road level

Reported via desktop in the Gully/Drainage category anonymously at 09:13, Tuesday 22 February 2022

Sent to Cheshire East Council less than a minute later. Council ref: 3333539.

Ref report 3282418 (and 3423799, 3431803, 3434821) I spoke to your passing gully cleaning team yesterday. They say they cannot clean a fully blocked gully until it has been jetted. (You can't even see where the gully is for the time being as it will be underwater until either you jet it or we have a dry spell.) You have promised to deal with it in the next 12 weeks (for which many thanks) but please can you ensure that you send a jetter/sludge removal team and not the normal gully cleaning vehicle because the latter cannot do anything.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for contacting Cheshire East Highways. We have logged your enquiry and passed it to a member of our team.

    Our teams are working hard to manage and respond to reports from members of the public.

    We are currently experiencing an increase in demand of reported issues along with a temporary reduction in available staff due to Covid-related sickness and self-isolation.

    During this time and until the situation improves, we will be prioritising those issues that present most risk to the travelling public. While we normally aim to provide you with a response within 20 working days, response times for all other reported issues may take longer than usual.

    Thank you for your patience.
    Our teams are working hard to manage and respond to reports from members of the public.

    We are currently experiencing an increase in demand of reported issues along with a temporary reduction in available staff due to Covid-related sickness and self-isolation.

    During this time and until the situation improves, we will be prioritising those issues that present most risk to the travelling public. While we normally aim to provide you with a response within 20 working days, response times for all other reported issues may take longer than usual.

    Thank you for your patience.

    Posted by Cheshire East Council at 09:13, Tuesday 22 February 2022

  • State changed to: In progress

    Updated by Cheshire East Council at 12:20, Monday 28 February 2022

  • State changed to: No further action

    Updated by Cheshire East Council at 13:13, Friday 20 May 2022

  • Thank you for contacting Cheshire East Highways. We have logged your enquiry and passed it to a member of our team.

    Our teams are working hard to manage and respond to reports from members of the public.

    We are currently experiencing an increase in demand of reported issues along with a temporary reduction in available staff due to Covid-related sickness and self-isolation.

    During this time and until the situation improves, we will be prioritising those issues that present most risk to the travelling public. While we normally aim to provide you with a response within 20 working days, response times for all other reported issues may take longer than usual.

    Thank you for your patience.

    State changed to: Open

    Posted by Cheshire East Council at 16:32, Friday 20 May 2022

  • State changed to: In progress

    Updated by Cheshire East Council at 16:34, Friday 20 May 2022

  • We have arranged for jetting work to be carried out. We post our upcoming jetting schedule online and usually update it on a weekly basis. The list shows the schedule for up to 2 weeks in advance. The list might change due to issues such as weather events, so you should check it for any updates. You can find the latest updates online through the following link: https://www.cheshireeast.gov.uk/ highways_and_roads/ road-maintenance/ gullies-and-drains.aspx

    State changed to: Action scheduled

    Posted by Cheshire East Council at 16:16, Monday 4 July 2022

  • We have assessed your report and have arranged to carry out work as soon as possible.

    Posted by Cheshire East Council at 07:58, Wednesday 6 July 2022

  • We are pleased to confirm that work is now complete, and your report has been closed.

    State changed to: Fixed

    Posted by Cheshire East Council at 14:43, Wednesday 20 July 2022

Only the original reporter may leave updates. If you made the original report please log in to leave an update.