Long damaged areas along the road between the two roundabouts dangerous and could be life threatening to a small scooter or motorcycle
Reported via mobile in the Pothole category anonymously at 14:06, Wed 16 February 2022
Sent to Cheshire East Council less than a minute later. Council ref: 3316106.
The road surface is showing signs of delaminating between the structure of the road. I looks like diesel was on the surface when the topping was lates down it looks eaten away.
Updates
-
Thank you for contacting Cheshire East Highways. We have logged your enquiry and passed it to a member of our team.
Our teams are working hard to manage and respond to reports from members of the public.
We are currently experiencing an increase in demand of reported issues along with a temporary reduction in available staff due to Covid-related sickness and self-isolation.During this time and until the situation improves, we will be prioritising those issues that present most risk to the travelling public. While we normally aim to provide you with a response within 20 working days, response times for all other reported issues may take longer than usual.
Thank you for your patience.
Our teams are working hard to manage and respond to reports from members of the public.
We are currently experiencing an increase in demand of reported issues along with a temporary reduction in available staff due to Covid-related sickness and self-isolation.During this time and until the situation improves, we will be prioritising those issues that present most risk to the travelling public. While we normally aim to provide you with a response within 20 working days, response times for all other reported issues may take longer than usual.
Thank you for your patience.
Posted by Cheshire East Council at 14:06, Wed 16 February 2022
-
State changed to: In progress
Updated by Cheshire East Council at 08:58, Thu 17 February 2022
-
A member of our team has been in touch via your preferred method of contact to give you an update on your report and let you know what will happen next.
Posted by Cheshire East Council at 08:55, Mon 28 February 2022
-
We deal with defects based on the level of immediate risk. We have assessed the issue and it does not present an immediate risk to highway users at this time. As the problem you have reported is not causing an immediate safety issue we will now look at the best long- term approach for this location. We keep all roads and highway assets safe through our routine inspections. If anything is identified as a risk during a future inspection, we will take action to deal with it as appropriate.
State changed to: No further action
Posted by Cheshire East Council at 08:52, Wed 8 June 2022
This report is now closed to updates from the public. You can make a new report in the same location.