You can move around with your keyboard
plus
minus
left
right
Drop pin on the map to start a new report
space
Press space again to adjust the location
space
Back to all reports

Gully/Drainage problem

Reported via Open311 in the Gully/Drainage category by Cheshire East Council at 11:32, Wednesday 9 February 2022

Sent to Cheshire East Council less than a minute later. Council ref: 3303346.

Gully/Drainage problem

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for contacting Cheshire East Highways. We have logged your enquiry and passed it to a member of our team.

    Our teams are working hard to manage and respond to reports from members of the public.

    We are currently experiencing an increase in demand of reported issues along with a temporary reduction in available staff due to Covid-related sickness and self-isolation.

    During this time and until the situation improves, we will be prioritising those issues that present most risk to the travelling public. While we normally aim to provide you with a response within 20 working days, response times for all other reported issues may take longer than usual.

    Thank you for your patience.
    Our teams are working hard to manage and respond to reports from members of the public.

    We are currently experiencing an increase in demand of reported issues along with a temporary reduction in available staff due to Covid-related sickness and self-isolation.

    During this time and until the situation improves, we will be prioritising those issues that present most risk to the travelling public. While we normally aim to provide you with a response within 20 working days, response times for all other reported issues may take longer than usual.

    Thank you for your patience.

    Posted by Cheshire East Council at 15:01, Thursday 10 February 2022

  • We have assessed the issue and added it to our improvement programme for repair over the longer term. This means we are unlikely to do any improvement work here during the current financial year. Our programmes sometimes change if more funding becomes available. You should check our website for any updates. You can find details of the work planned for this location and where it currently sits on the programme through our website: https://www.cheshireeast.gov.uk/ highways_and_roads/ road-maintenance/ road-repair-and-improvement-programme-2021-2022/ road-repair-and-improvement-programme-2021-2022.aspx

    State changed to: Closed

    Posted by Cheshire East Council at 15:39, Monday 14 February 2022

  • State changed to: In progress

    Updated by Cheshire East Council at 10:59, Thursday 24 February 2022

  • We have arranged for jetting work to be carried out. We post our upcoming jetting schedule online and usually update it on a weekly basis. The list shows the schedule for up to 2 weeks in advance. The list might change due to issues such as weather events, so you should check it for any updates. You can find the latest updates online through the following link: https://www.cheshireeast.gov.uk/ highways_and_roads/ road-maintenance/ gullies-and-drains.aspx

    State changed to: Action scheduled

    Posted by Cheshire East Council at 12:50, Thursday 24 February 2022

Only the original reporter may leave updates. If you made the original report please log in to leave an update.